BIOROCK-S Installation in Berkshire

BIOROCK-S Installation in Berkshire

Location

Maidenhead, Berkshire

Project

2 Bedroom Annex with Studio.

System

BIOROCK-S System with ST1-2000 Primary Tank & BIOROCK-S Treatment Unit

Background

The client had the option to connect to the mains but the costs, permitting time and access permits proved prohibitive. As the plant was to be located quite close to the building the client also wanted a plant without noise and with minimum maintenance. It was also planned to discharge to a nearby stream and required a high quality final effluent.

Installation

Installation was carried out by the clients contractor under the supervision of a BIOROCK engineer and was completed in less than 2 days.

Vai vēlaties ar mums sazināties?

Labdien, mans vārds ir José Manuel Rodríguez , BIOROCK International Sales Director . Sazinieties ar mums, lai saņemtu BEZMAKSAS projekta novērtējumu.

Kur jūs atrodaties?

Par jums?

Lai sazinātos ar jums

Tel. nr. valsts kods tiek izvēlēts automātiski pēc valsts izvēles.

Kāda veida produkts jūs interesē?

Ja izvēlaties citu, lūdzu, norādiet to piezīmju laukā.

Kā mēs varam jums palīdzēt?